Construction Schedule


The following tables reflect the approximate construction start and completion dates for selected FDOT major construction projects.

Present Construction

FDOT Financial Project No. Location Construction Activities Start Estimated Completion
2224691 I-110 from Brent Lane to Creighton Blvd. Brent / Airport Split Diamond Interchange FEB 07 FEB 08
4113931 Scenic Hwy from Hyde Park to Hwy 90. Resurfacing FEB 07 FEB 08
2224341
I-10/I-110 Interchange
Major Interchange Construction SEP 02 SEP 07
2224661
I-110 from Fairfield Dr. to Airport Blvd.
Add Lanes and Reconstruct MAR 04 MAR 08
2224671
I-110 from Maxwell Street to Fairfield Dr.
Minor Interchange Construction MAR 04 MAR 08

Future Construction

FDOT Financial Project No. Location Construction Activities Tentative Start Estimated Completion
There are no future construction projects scheduled at this time.

Completed Construction

FDOT Financial Project No. Location Construction Activities Started Completed
2186811
Alcaniz Street / MLK from 36th Ave. to Gregory St.
Resurfacing MAY 04 SEP 04
2186791 Pine Forest Rd. from Longleaf Dr. to I-10 Resurfacing JAN 03 AUG 03
2186801 US 90 from US 90A to Godwin Lane Resurfacing FEB 03 JUN 03
2186681 SR 296 from US 90 to 12th Ave. Resurfacing JUN 03 FEB 04
2186771 US 90 from Edison Rd. to Lynch Rd. Resurfacing JUL 03 OCT 03
2186781
Pace Boulevard from Bayou Chico Bridge to SR 96
Resurfacing DEC 03 FEB 05
4113871 Mobile Hwy. from Lynch to V St. Resurfacing JAN 05 JUL 05
4066201 Ten Mile Rd. (Greenbriar Blvd.) Resurfacing JAN 05 AUG 05
4113941 Sorrento Rd. from Blue Angel to Gulf Beach. Resurfacing FEB 05 OCT 05
2204021
SR 87 from SR 30 to North of Five Forks Rd.
Multi-Lane Reconstruction AUG 02 NOV 05
4063211 9th Ave. from Crieghton Rd. to Dunmire Rd. Resurfacing JAN 05 MAY 05
4090081 US 90 at Summit Blvd. Interchange Reconstruction MAR 05 OCT 05
2186961
Cervantes Street Bridge (Railroad Overpass)
Bridge Replacement AUG 04 JAN 06
4063311 Airport Blvd. from 9th Ave. to 12th Ave. Resurfacing OCT 05 JAN 06
2185391 Davis Highway from I-10 to Langley Ave. Add Lanes and Reconstruct APR 05 OCT 06
4052711 US 90 at Pine Forest Rd. Intersection and Drainage Improvements JAN 06 NOV 06
4163783 Olive Road from Old Palafox to Scenic Hwy Shoulder Paving JAN 06 NOV 06

 

Home | Florida 511 | Description | Traffic | News & Information | FAQ | Links | Contact

Volkert Construction
Florida Department of Transportation Designed & Hosted By PBS&J Ventura Consulting Group
       
Get the newest version of the Macromedia Flash Player. Get the newest version of Adobe Acrobat Reader.